BetaActiveBatteryTECLBNL
20 MW storage in Hillsborough, FL · In queue since October 2024 · Proposed COD December 2025
20 MW
Capacity
1
Components
Battery
1y 5m
In Queue
System Impact Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
1y 2m
Schedule
4 months past proposed COD
Impact Study25%
Queue EntryOct 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
FL
County
Hillsborough
Region
Southeast
Developer
—
Utility
Tampa Electric Company
Entity
TEC
Point of Interconnection
Gannon Substation, Hillsborough County
Data Source
LBNL
No news available for this project.