74.5 MW generation in Hillsborough, FL · In queue since March 2024 · Proposed COD December 2026
74.5 MW
Capacity
1
Components
Solar
2 years
In Queue
Cluster Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 9m
Impact Study25%
Queue EntryMar 31, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
FL
County
Hillsborough
Region
Southeast
Developer
—
Utility
Tampa Electric Company
Entity
TEC
Point of Interconnection
Sun City Substation, Hillsborough County
Data Source
LBNL
No news available for this project.