BetaActiveSolarTECLBNL
52 MW generation in Polk, FL · In queue since March 2024 · Proposed COD December 2027
52 MW
Capacity
1
Components
Solar
2 years
In Queue
Cluster Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 9m
Impact Study25%
Queue EntryMar 27, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
FL
County
Polk
Region
Southeast
Developer
—
Utility
Tampa Electric Company
Entity
TEC
Point of Interconnection
Pebbledale Substation, Polk County
Data Source
LBNL
No news available for this project.