BetaActiveGasCoalTECLBNL
21 MW hybrid in Polk, FL · In queue since March 2023 · Proposed COD April 2024
21 MW
Capacity
1
Components
Gas
3 years
In Queue
Cluster Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 1m
Schedule
24 months past proposed COD
Impact Study25%
Queue EntryMar 13, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-04-01
Project Details
State
FL
County
Polk
Region
Southeast
Developer
—
Utility
Tampa Electric Company
Entity
TEC
Point of Interconnection
Polk Substation, Polk County
Data Source
LBNL