BetaActiveGasSRPLBNL
332 MW generation in Pinal, AZ · In queue since May 2021 · Proposed COD June 2026
332 MW
Capacity
1
Components
Gas
4y 10m
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 1m
Pre-Study0%
Queue EntryMay 6, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
AZ
County
Pinal
Region
West
Developer
—
Utility
Salt River Project
Entity
SRP
Point of Interconnection
Pinal Central-Browning 500 kV Line
Data Source
LBNL
No news available for this project.