BetaActiveGasSRPLBNL
17 MW generation in Pinal, AZ · In queue since June 2020 · Proposed COD December 2020
17 MW
Capacity
1
Components
Gas
5y 9m
In Queue
—
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
6 months
Schedule
65 months past proposed COD
Pre-Study0%
Queue EntryJun 19, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-12-01
Project Details
State
AZ
County
Pinal
Region
West
Developer
—
Utility
Salt River Project
Entity
SRP
Point of Interconnection
Desert Basin 230 kV
Data Source
LBNL
No news available for this project.