— Project Summary

Queue ID
SRP-SRP-Q64
Capacity
17 MW
Technology
Gas
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status

BetaActiveGasSRPLBNL

17 MW generation in Pinal, AZ · In queue since June 2020 · Proposed COD December 2020

17 MW

Capacity

1

Components

Gas

5y 9m

In Queue

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

6 months

Schedule

65 months past proposed COD

Pre-Study0%
Queue EntryJun 19, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2020-12-01

Project Details

State

AZ

County

Pinal

Region

West

Developer

Utility

Salt River Project

Entity

SRP

Point of Interconnection

Desert Basin 230 kV

Data Source

LBNL

No news available for this project.