BetaActiveSolarBatterySRPLBNL
600 MW hybrid in Pinal, AZ · In queue since January 2020 · Proposed COD May 2025
600 MW
Capacity
1
Components
Solar
6y 2m
In Queue
—
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5y 4m
Schedule
11 months past proposed COD
Pre-Study0%
Queue EntryJan 28, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-05-01
Project Details
State
AZ
County
Pinal
Region
West
Developer
—
Utility
Salt River Project
Entity
SRP
Point of Interconnection
Abel 230 kV
Data Source
LBNL
No news available for this project.