— Project Summary

Queue ID
SRP-SRP-Q50
Capacity
250 MW
Technology
Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status

BetaActiveBatterySRPLBNL

250 MW storage in Maricopa, AZ · In queue since October 2018 · Proposed COD May 2022

250 MW

Capacity

1

Components

Battery

7y 5m

In Queue

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 7m

Schedule

48 months past proposed COD

Pre-Study0%
Queue EntryOct 5, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-05-01

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Salt River Project

Entity

SRP

Point of Interconnection

Browning 230 kV

Data Source

LBNL

No news available for this project.