BetaActiveBatterySRPLBNL
250 MW storage in Maricopa, AZ · In queue since October 2018 · Proposed COD May 2022
250 MW
Capacity
1
Components
Battery
7y 5m
In Queue
—
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
3y 7m
Schedule
48 months past proposed COD
Pre-Study0%
Queue EntryOct 5, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-05-01
Project Details
State
AZ
County
Maricopa
Region
West
Developer
—
Utility
Salt River Project
Entity
SRP
Point of Interconnection
Browning 230 kV
Data Source
LBNL
No news available for this project.