— Project Summary

Queue ID
SRP_PV-PC-PV-PC-Q32
Capacity
928 MW
Technology
Battery
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status

BetaActiveGasBatterySRP_PV-PCLBNL

928 MW hybrid in Pinal, AZ · In queue since August 2023 · Proposed COD November 2026

928 MW

Capacity

1

Components

Gas

2y 7m

In Queue

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 3m

Pre-Study0%
Queue EntryAug 17, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-11-05

Project Details

State

AZ

County

Pinal

Region

West

Developer

Utility

Salt River Project

Entity

SRP_PV-PC

Point of Interconnection

Pinal Central-Duke 500 kV Line

Data Source

LBNL

No news available for this project.