BetaActiveGasBatterySRP_PV-PCLBNL
928 MW hybrid in Pinal, AZ · In queue since August 2023 · Proposed COD November 2026
928 MW
Capacity
1
Components
Gas
2y 7m
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 3m
Pre-Study0%
Queue EntryAug 17, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-11-05
Project Details
State
AZ
County
Pinal
Region
West
Developer
—
Utility
Salt River Project
Entity
SRP_PV-PC
Point of Interconnection
Pinal Central-Duke 500 kV Line
Data Source
LBNL
No news available for this project.