— Project Summary

Queue ID
SRP_PV-PC-PV-PC-Q09
Capacity
400 MW
Technology
Solar+Battery
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status

BetaActiveSolarBatterySRP_PV-PCLBNL

400 MW hybrid in Pinal, AZ · In queue since September 2018 · Proposed COD December 2023

400 MW

Capacity

1

Components

Solar

7y 6m

In Queue

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

5y 3m

Schedule

27 months past proposed COD

Pre-Study0%
Queue EntrySep 12, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-31

Project Details

State

AZ

County

Pinal

Region

West

Developer

Utility

Salt River Project

Entity

SRP_PV-PC

Point of Interconnection

Pinal Central 230 kV

Data Source

LBNL

No news available for this project.