400 MW hybrid in Pinal, AZ · In queue since September 2018 · Proposed COD December 2023
400 MW
Capacity
1
Components
Solar
7y 6m
In Queue
—
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
5y 3m
Schedule
27 months past proposed COD
Pre-Study0%
Queue EntrySep 12, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
AZ
County
Pinal
Region
West
Developer
—
Utility
Salt River Project
Entity
SRP_PV-PC
Point of Interconnection
Pinal Central 230 kV
Data Source
LBNL