— Project Summary

Queue ID
SRP-Cluster 24-Q2417
Capacity
843.2 MW
Technology
Solar+Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status

BetaActiveSolarBatterySRPLBNL

843.2 MW hybrid in Maricopa, AZ · In queue since February 2024 · Proposed COD December 2028

843.2 MW

Capacity

1

Components

Solar

2y 1m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 10m

Pre-Study0%
Queue EntryFeb 5, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Salt River Project

Entity

SRP

Point of Interconnection

Pinal West-Jojoba 500 kV Line

Data Source

LBNL

No news available for this project.