— Project Summary

Queue ID
SRP-Cluster 24-Q2413
Capacity
409 MW
Technology
Battery
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status

BetaActiveBatterySRPLBNL

409 MW storage in Pinal, AZ · In queue since February 2024 · Proposed COD December 2027

409 MW

Capacity

1

Components

Battery

2y 1m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 10m

Pre-Study0%
Queue EntryFeb 5, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Project Details

State

AZ

County

Pinal

Region

West

Developer

Utility

Salt River Project

Entity

SRP

Point of Interconnection

Randolph-Abel 230 kV Line

Data Source

LBNL