BetaActiveBatterySRPLBNL
409 MW storage in Pinal, AZ · In queue since February 2024 · Proposed COD December 2027
409 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 10m
Pre-Study0%
Queue EntryFeb 5, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
AZ
County
Pinal
Region
West
Developer
—
Utility
Salt River Project
Entity
SRP
Point of Interconnection
Randolph-Abel 230 kV Line
Data Source
LBNL
No news available for this project.