BetaActiveSolarBatterySRP_ANPPLBNL
800 MW hybrid in Maricopa, AZ · In queue since February 2023 · Proposed COD June 2027
800 MW
Capacity
1
Components
Solar
3y 1m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 4m
Pre-Study0%
Queue EntryFeb 8, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
AZ
County
Maricopa
Region
West
Developer
—
Utility
Salt River Project
Entity
SRP_ANPP
Point of Interconnection
Hassayampa 500 kV
Data Source
LBNL
No news available for this project.