— Project Summary

Queue ID
SRP_ANPP-ANPP HVS-Q37
Capacity
130 MW
Technology
Gas
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status

BetaActiveGasSRP_ANPPLBNL

130 MW generation in Maricopa, AZ · In queue since February 2023 · Proposed COD April 2024

130 MW

Capacity

1

Components

Gas

3y 1m

In Queue

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

1y 2m

Schedule

24 months past proposed COD

Pre-Study0%
Queue EntryFeb 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-04-16

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Salt River Project

Entity

SRP_ANPP

Point of Interconnection

Hassayampa 500 kV

Data Source

LBNL