BetaActiveGasSRP_ANPPLBNL
77 MW generation in Maricopa, AZ · In queue since September 2022 · Proposed COD March 2024
77 MW
Capacity
1
Components
Gas
3y 6m
In Queue
—
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 6m
Schedule
24 months past proposed COD
Pre-Study0%
Queue EntrySep 2, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-03-31
Project Details
State
AZ
County
Maricopa
Region
West
Developer
—
Utility
Salt River Project
Entity
SRP_ANPP
Point of Interconnection
Hassayampa 500 kV
Data Source
LBNL
No news available for this project.