— Project Summary

Queue ID
SRP_ANPP-ANPP HVS-Q29
Capacity
500 MW
Technology
Solar+Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status

BetaActiveSolarBatterySRP_ANPPLBNL

500 MW hybrid in Maricopa, AZ · In queue since June 2021 · Proposed COD December 2027

500 MW

Capacity

1

Components

Solar

4y 9m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

6y 6m

Pre-Study0%
Queue EntryJun 24, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Salt River Project

Entity

SRP_ANPP

Point of Interconnection

Hassayampa 500 kV

Data Source

LBNL

No news available for this project.