— Project Summary

Queue ID
SRP_ANPP-ANPP HVS-Q22
Capacity
125 MW
Technology
Solar
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status

BetaActiveSolarSRP_ANPPLBNL

125 MW generation in Maricopa, AZ · In queue since February 2016 · Proposed COD December 2025

125 MW

Capacity

1

Components

Solar

10y 1m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

9y 10m

Schedule

3 months past proposed COD

Pre-Study0%
Queue EntryFeb 11, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Salt River Project

Entity

SRP_ANPP

Point of Interconnection

Hassayampa 500 kV

Data Source

LBNL

No news available for this project.