— Project Summary

Queue ID
SPP-GEN-2026-SR5
Capacity
200 MW
Technology
Battery
Status
active
Location
Wellington, KS
Region
SPP
Developer
IA Status

BetaActiveBattery/StorageSPPLive · SPP

200 MW storage in Wellington, KS · In queue since January 2026

200 MW

Capacity

0

Components

2 months

In Queue

IA Status

Interconnection Timeline

Total Duration

2 months

Pre-Study0%
Queue EntryJan 20, 2026

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

KS

County

Wellington

Region

SPP

Developer

Utility

WERE

Entity

SPP

Point of Interconnection

Sumner 138kV

Data Source

Live · SPP

No news available for this project.