— Project Summary

Queue ID
SPP-GEN-2026-SR11
Capacity
258 MW
Technology
Battery
Status
active
Location
Mill Creek, OK
Region
SPP
Developer
IA Status

BetaActiveBattery/StorageSPPLive · SPP

258 MW storage in Mill Creek, OK · In queue since January 2026

258 MW

Capacity

0

Components

2 months

In Queue

IA Status

Interconnection Timeline

Total Duration

2 months

Pre-Study0%
Queue EntryJan 26, 2026

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

OK

County

Mill Creek

Region

SPP

Developer

Utility

OGE

Entity

SPP

Point of Interconnection

Johnson County 345kV Substation

Data Source

Live · SPP

No news available for this project.