BetaActiveBattery/StorageSPPLive · SPP
60.4 MW storage in Goultry, OK · In queue since January 2026
60.4 MW
Capacity
0
Components
2 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
2 months
Pre-Study0%
Queue EntryJan 7, 2026
Interconnection request submitted to ISO/RTO
DISIS Study
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
OK
County
Goultry
Region
SPP
Developer
—
Utility
OG&E
Entity
SPP
Point of Interconnection
Woodring 345kV Substation
Data Source
Live · SPP
No news available for this project.