Queue ID
SPP-GEN-2025-SR9
Capacity
400 MW
Technology
Gas
Status
active
Location
Fort Gibson, OK
Region
SPP
Developer
IA Status

BetaActiveThermalSPPLive · SPP

400 MW generation in Fort Gibson, OK · In queue since May 2025

400 MW

Capacity

0

Components

10 months

In Queue

IA Status

Interconnection Timeline

Total Duration

10 months

Pre-Study0%
Queue EntryMay 31, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

OK

County

Fort Gibson

Region

SPP

Developer

Utility

OG&E

Entity

SPP

Point of Interconnection

Muskogee 345 KV Substation

Data Source

Live · SPP