150 MW storage in Kinsley, KS · In queue since August 2025
150 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
7 months
Pre-Study0%
Queue EntryAug 18, 2025
Interconnection request submitted to ISO/RTO
DISIS Study
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
KS
County
Kinsley
Region
SPP
Developer
—
Utility
SUNC
Entity
SPP
Point of Interconnection
Great Bend-Spearville 230kV line
Data Source
Live · SPP
No news available for this project.