— Project Summary

Queue ID
SPP-GEN-2025-SR20
Capacity
100 MW
Technology
Gas
Status
active
Location
Omaha, NE
Region
SPP
Developer
IA Status

BetaActiveThermalSPPLive · SPP

100 MW generation in Omaha, NE · In queue since June 2025

100 MW

Capacity

0

Components

9 months

In Queue

IA Status

Interconnection Timeline

Total Duration

9 months

Pre-Study0%
Queue EntryJun 12, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

NE

County

Omaha

Region

SPP

Developer

Utility

OPPD

Entity

SPP

Point of Interconnection

SUBSTATION LOOP IN OPPD LINES S1211 TO S1220 AND S1211 TO S1299

Data Source

Live · SPP

No news available for this project.