— Project Summary

Queue ID
SPP-GEN-2025-SR18
Capacity
50 MW
Technology
Gas
Status
active
Location
Indepedence, MO
Region
SPP
Developer
IA Status

BetaActiveThermalSPPLive · SPP

50 MW generation in Indepedence, MO · In queue since June 2025

50 MW

Capacity

0

Components

9 months

In Queue

IA Status

Interconnection Timeline

Total Duration

9 months

Pre-Study0%
Queue EntryJun 12, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

MO

County

Indepedence

Region

SPP

Developer

Utility

INDN

Entity

SPP

Point of Interconnection

Blue Valley 161kV Substation

Data Source

Live · SPP