— Project Summary

Queue ID
SPP-GEN-2025-SR15
Capacity
125 MW
Technology
Gas
Status
active
Location
Newcastle, OK
Region
SPP
Developer
IA Status

BetaActiveThermalSPPLive · SPP

125 MW generation in Newcastle, OK · In queue since May 2025

125 MW

Capacity

0

Components

10 months

In Queue

IA Status

Interconnection Timeline

Total Duration

10 months

Pre-Study0%
Queue EntryMay 31, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

OK

County

Newcastle

Region

SPP

Developer

Utility

OG&E

Entity

SPP

Point of Interconnection

McClain Substation

Data Source

Live · SPP

No news available for this project.