— Project Summary

Queue ID
SPP-GEN-2025-GR6
Capacity
300 MW
Technology
Wind
Status
active
Location
Dimmit, TX
Region
SPP
Developer
IA Status

BetaActiveWindSPPLive · SPP

300 MW generation in Dimmit, TX · In queue since November 2025

300 MW

Capacity

0

Components

4 months

In Queue

IA Status

Interconnection Timeline

Total Duration

4 months

Pre-Study0%
Queue EntryNov 7, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

TX

County

Dimmit

Region

SPP

Developer

Utility

SPS

Entity

SPP

Point of Interconnection

Castro County 115kV

Data Source

Live · SPP

No news available for this project.