BetaActiveWindSPPLive · SPP
120 MW generation in Elida, NM · In queue since June 2025
120 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
9 months
Pre-Study0%
Queue EntryJun 30, 2025
Interconnection request submitted to ISO/RTO
DISIS Study
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NM
County
Elida
Region
SPP
Developer
—
Utility
SPS
Entity
SPP
Point of Interconnection
San Juan Mesa 230 kV Substation
Data Source
Live · SPP
No news available for this project.