— Project Summary

Queue ID
SPP-GEN-2024-SR9
Capacity
150 MW
Technology
Battery
Status
active
Location
Beaver, OK
Region
SPP
Developer
IA Status
IA Pending

BetaActiveBatterySPPLBNL + Live

150 MW storage in Beaver, OK · In queue since January 2024 · Proposed COD January 2027

150 MW

Capacity

1

Components

Battery

2y 2m

In Queue

IA Pending

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3 years

In Study38%
Queue EntryJan 26, 2024

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-01-01

Project Details

State

OK

County

Beaver

Region

SPP

Developer

Utility

OG&E

Entity

SPP

Point of Interconnection

Beaver County Substation 345 kV

Data Source

LBNL + Live

No news available for this project.