— Project Summary

Queue ID
SPP-GEN-2024-SR8
Capacity
70 MW
Technology
Battery
Status
active
Location
Greeley, NE
Region
SPP
Developer
IA Status
Facility Study

BetaActiveBatterySPPLBNL + Live

70 MW storage in Greeley, NE · In queue since April 2024 · Proposed COD December 2026

70 MW

Capacity

1

Components

Battery

1y 11m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 8m

Facilities Study50%
Queue EntryApr 3, 2024

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

NE

County

Greeley

Region

SPP

Developer

Utility

NPPD

Entity

SPP

Point of Interconnection

Spalding to North Loup 115kV

Data Source

LBNL + Live

No news available for this project.