BetaActiveSolarSPPLBNL + Live
200 MW generation in Beaver, OK · In queue since January 2024 · Proposed COD June 2027
200 MW
Capacity
1
Components
Solar
2y 2m
In Queue
IA Pending
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 5m
In Study38%
Queue EntryJan 26, 2024
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
OK
County
Beaver
Region
SPP
Developer
—
Utility
OG&E
Entity
SPP
Point of Interconnection
Beaver County Substation 345 kV
Data Source
LBNL + Live
No news available for this project.