200 MW storage in Johnston, OK · In queue since February 2024
200 MW
Capacity
1
Components
Battery
2y 1m
In Queue
IA Pending
IA Status
Interconnection Timeline
Total Duration
2y 1m
In Study38%
Queue EntryFeb 20, 2024
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
OK
County
Johnston
Region
SPP
Developer
—
Utility
OG&E
Entity
SPP
Point of Interconnection
Interconnecting at Hugo - Sunnyside 345 kV transmission line
Data Source
LBNL + Live