BetaActiveBatterySPPLBNL + Live
154.6 MW storage in Kay, OK · In queue since December 2024 · Proposed COD May 2027
154.6 MW
Capacity
1
Components
Battery
1y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 5m
In Study38%
Queue EntryDec 26, 2024
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-05-01
Project Details
State
OK
County
Kay
Region
SPP
Developer
—
Utility
OG&E
Entity
SPP
Point of Interconnection
Tap Medford Tap _x0013_ Coyote 138kV
Data Source
LBNL + Live
No news available for this project.