BetaActiveBatterySPPLBNL + Live
52.2 MW storage in Bryan, OK · In queue since May 2024 · Proposed COD June 2026
52.2 MW
Capacity
1
Components
Battery
1y 10m
In Queue
IA Pending
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 1m
In Study38%
Queue EntryMay 1, 2024
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
OK
County
Bryan
Region
SPP
Developer
—
Utility
OG&E
Entity
SPP
Point of Interconnection
Brown 138kV Substation
Data Source
LBNL + Live
No news available for this project.