— Project Summary

Queue ID
SPP-GEN-2024-SR13
Capacity
52.2 MW
Technology
Battery
Status
active
Location
Bryan, OK
Region
SPP
Developer
IA Status
IA Pending

BetaActiveBatterySPPLBNL + Live

52.2 MW storage in Bryan, OK · In queue since May 2024 · Proposed COD June 2026

52.2 MW

Capacity

1

Components

Battery

1y 10m

In Queue

IA Pending

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 1m

In Study38%
Queue EntryMay 1, 2024

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-01

Project Details

State

OK

County

Bryan

Region

SPP

Developer

Utility

OG&E

Entity

SPP

Point of Interconnection

Brown 138kV Substation

Data Source

LBNL + Live

No news available for this project.