BetaActiveBatterySPPLBNL + Live
20 MW storage in Lamoure, ND · In queue since May 2024 · Proposed COD October 2026
20 MW
Capacity
1
Components
Battery
1y 10m
In Queue
IA Pending
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 5m
In Study38%
Queue EntryMay 21, 2024
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-10-01
Project Details
State
ND
County
Lamoure
Region
SPP
Developer
—
Utility
WAPA
Entity
SPP
Point of Interconnection
Edgeley 115 kV Substation
Data Source
LBNL + Live
No news available for this project.