BetaActiveBatterySPPLBNL + Live
80 MW storage in Lancaster, NE · In queue since April 2024 · Proposed COD December 2026
80 MW
Capacity
1
Components
Battery
1y 11m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 8m
Facilities Study50%
Queue EntryApr 22, 2024
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
NE
County
Lancaster
Region
SPP
Developer
—
Utility
NPPD
Entity
SPP
Point of Interconnection
Monolith 115kV
Data Source
LBNL + Live
No news available for this project.