BetaActiveSolarSPPLBNL + Live
196 MW generation in Lea, NM · In queue since June 2024 · Proposed COD April 2027
196 MW
Capacity
1
Components
Solar
1y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 10m
In Study38%
Queue EntryJun 7, 2024
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-01
Project Details
State
NM
County
Lea
Region
SPP
Developer
—
Utility
Xcel/SPS
Entity
SPP
Point of Interconnection
230kV Cunningham Substation
Data Source
LBNL + Live
No news available for this project.