BetaActiveSolar / PhotovoltaicSPPLive · SPP
142.183 MW generation in Sabine, TX · In queue since March 2025
142.183 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Interconnection Timeline
Total Duration
1 year
Pre-Study0%
Queue EntryMar 1, 2025
Interconnection request submitted to ISO/RTO
DISIS Study
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
TX
County
Sabine
Region
SPP
Developer
—
Utility
ETEC
Entity
SPP
Point of Interconnection
Hemphill 138 kV Substation
Data Source
Live · SPP
No news available for this project.