— Project Summary

Queue ID
SPP-GEN-2024-345
Capacity
600 MW
Technology
Wind
Status
active
Location
Nowata, OK
Region
SPP
Developer
IA Status

BetaActiveWind / WindSPPLive · SPP

600 MW generation in Nowata, OK · In queue since March 2025

600 MW

Capacity

0

Components

1 year

In Queue

IA Status

Interconnection Timeline

Total Duration

1 year

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

OK

County

Nowata

Region

SPP

Developer

Utility

AEP

Entity

SPP

Point of Interconnection

Delaware 345 kV Substation

Data Source

Live · SPP

No news available for this project.