— Project Summary

Queue ID
SPP-GEN-2024-326
Capacity
225 MW
Technology
Battery
Status
active
Location
Stark, ND
Region
SPP
Developer
IA Status

BetaActiveBattery/Storage / BatterySPPLive · SPP

225 MW storage in Stark, ND · In queue since March 2025

225 MW

Capacity

0

Components

1 year

In Queue

IA Status

Interconnection Timeline

Total Duration

1 year

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

ND

County

Stark

Region

SPP

Developer

Utility

WAPA

Entity

SPP

Point of Interconnection

Belfield 230 kV Substation

Data Source

Live · SPP

No news available for this project.