— Project Summary

Queue ID
SPP-GEN-2024-322
Capacity
75 MW
Technology
Battery
Status
active
Location
Graham, KS
Region
SPP
Developer
IA Status

BetaActiveBattery/Storage / BatterySPPLive · SPP

75 MW storage in Graham, KS · In queue since March 2025

75 MW

Capacity

0

Components

1 year

In Queue

IA Status

Interconnection Timeline

Total Duration

1 year

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

KS

County

Graham

Region

SPP

Developer

Utility

MIDW

Entity

SPP

Point of Interconnection

Redlin - Beach3 115 kV line

Data Source

Live · SPP

No news available for this project.