— Project Summary

Queue ID
SPP-GEN-2024-308
Capacity
199 MW
Technology
Wind+Battery
Status
active
Location
Woodward, OK
Region
SPP
Developer
IA Status

BetaActiveHybrid / Wind/StorageSPPLive · SPP

199 MW generation in Woodward, OK · In queue since March 2025

199 MW

Capacity

0

Components

1 year

In Queue

IA Status

Interconnection Timeline

Total Duration

1 year

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

OK

County

Woodward

Region

SPP

Developer

Utility

WFEC

Entity

SPP

Point of Interconnection

Okeene - Mooreland 138 kV line

Data Source

Live · SPP

No news available for this project.