— Project Summary

Queue ID
SPP-GEN-2024-299
Capacity
744 MW
Technology
Gas
Status
active
Location
Oklahoma, OK
Region
SPP
Developer
IA Status

BetaActiveThermal / GasSPPLive · SPP

744 MW generation in Oklahoma, OK · In queue since March 2025

744 MW

Capacity

0

Components

1 year

In Queue

IA Status

Interconnection Timeline

Total Duration

1 year

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

OK

County

Oklahoma

Region

SPP

Developer

Utility

OGE

Entity

SPP

Point of Interconnection

AES 5 345 kV Substation

Data Source

Live · SPP

No news available for this project.