— Project Summary

Queue ID
SPP-GEN-2024-284
Capacity
199 MW
Technology
Solar
Status
active
Location
Mercer, ND
Region
SPP
Developer
IA Status

BetaActiveSolar / PhotovoltaicSPPLive · SPP

199 MW generation in Mercer, ND · In queue since March 2025

199 MW

Capacity

0

Components

1 year

In Queue

IA Status

Interconnection Timeline

Total Duration

1 year

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

ND

County

Mercer

Region

SPP

Developer

Utility

BEPC

Entity

SPP

Point of Interconnection

Antelope Valley - Broadland 345 kV Line

Data Source

Live · SPP