— Project Summary

Queue ID
SPP-GEN-2024-277
Capacity
150 MW
Technology
Battery
Status
active
Location
Shawnee, KS
Region
SPP
Developer
IA Status

BetaActiveBattery/Storage / BatterySPPLive · SPP

150 MW storage in Shawnee, KS · In queue since March 2025

150 MW

Capacity

0

Components

1 year

In Queue

IA Status

Interconnection Timeline

Total Duration

1 year

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

KS

County

Shawnee

Region

SPP

Developer

Utility

WERE

Entity

SPP

Point of Interconnection

Tecumseh Hill - Swissvale 230kV Line

Data Source

Live · SPP

No news available for this project.