— Project Summary

Queue ID
SPP-GEN-2024-265
Capacity
155 MW
Technology
Solar+Battery
Status
active
Location
Lea, NM
Region
SPP
Developer
IA Status

BetaActiveHybrid / Solar/StorageSPPLive · SPP

155 MW generation in Lea, NM · In queue since March 2025

155 MW

Capacity

0

Components

1 year

In Queue

IA Status

Interconnection Timeline

Total Duration

1 year

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

NM

County

Lea

Region

SPP

Developer

Utility

SPS

Entity

SPP

Point of Interconnection

Bensing 115 kV Substation

Data Source

Live · SPP