— Project Summary

Queue ID
SPP-GEN-2024-177
Capacity
199 MW
Technology
Battery
Status
active
Location
Bossier Parish, LA
Region
SPP
Developer
IA Status

BetaActiveBattery/Storage / BatterySPPLive · SPP

199 MW storage in Bossier Parish, LA · In queue since March 2025

199 MW

Capacity

0

Components

1 year

In Queue

IA Status

Interconnection Timeline

Total Duration

1 year

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

LA

County

Bossier Parish

Region

SPP

Developer

Utility

AEP

Entity

SPP

Point of Interconnection

Red Point 138 kV Substation

Data Source

Live · SPP

No news available for this project.