— Project Summary

Queue ID
SPP-GEN-2024-141
Capacity
424 MW
Technology
Wind
Status
active
Location
Mercer, ND
Region
SPP
Developer
IA Status

BetaActiveWind / WindSPPLive · SPP

424 MW generation in Mercer, ND · In queue since March 2025

424 MW

Capacity

0

Components

1 year

In Queue

IA Status

Interconnection Timeline

Total Duration

1 year

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

ND

County

Mercer

Region

SPP

Developer

Utility

BEPC

Entity

SPP

Point of Interconnection

BASIN__-BE4 230 kV Substation

Data Source

Live · SPP

No news available for this project.