167 MW storage in Lawrence, MO · In queue since October 2024 · Proposed COD November 2028
167 MW
Capacity
1
Components
Battery
1y 5m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 1m
Impact Study25%
Queue EntryOct 30, 2024
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-11-25
Project Details
State
MO
County
Lawrence
Region
SPP
Developer
—
Utility
AEP
Entity
SPP
Point of Interconnection
Reeds Spring - Aurora 161 kV Line
Data Source
LBNL + Live
No news available for this project.