— Project Summary

Queue ID
SPP-GEN-2024-083
Capacity
250 MW
Technology
Solar
Status
active
Location
Choctaw, OK
Region
SPP
Developer
IA Status
System Impact Study

BetaActiveSolarSPPLBNL + Live

250 MW generation in Choctaw, OK · In queue since October 2024 · Proposed COD December 2029

250 MW

Capacity

1

Components

Solar

1y 5m

In Queue

System Impact Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 2m

Impact Study25%
Queue EntryOct 30, 2024

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-31

Project Details

State

OK

County

Choctaw

Region

SPP

Developer

Utility

WFEC

Entity

SPP

Point of Interconnection

Hugo 345 kV Substation

Data Source

LBNL + Live

No news available for this project.