256 MW generation in Lamb, TX · In queue since October 2024 · Proposed COD December 2027
256 MW
Capacity
1
Components
Solar
1y 5m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 2m
Impact Study25%
Queue EntryOct 30, 2024
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
TX
County
Lamb
Region
SPP
Developer
—
Utility
SPS
Entity
SPP
Point of Interconnection
Plant X 230 kV Substation
Data Source
LBNL + Live